File #: Res. 2016-084    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/1/2016 In control: City Council
On agenda: 8/2/2016 Final action: 8/2/2016
Title: Consideration to increase funding for the Arbor Street Crosswalk Improvements.
Attachments: 1. 1 - Res. 1 Funding Increase, 2. 2 - Res 2 - No RRFB, 3. 3 - Res 3 - No RRFB or bumpout
City Council Meeting Date: August 2, 2016

To: Mayor and City Council
City Administrator

From: David Bennett - Public Works Director/City Engineer

Title
Consideration to increase funding for the Arbor Street Crosswalk Improvements.

Body
Action Requested:
Staff recommends approval of the Resolution authorizing additional funding for the Crosswalk Improvements at the intersection of Trunk Highway 246 and Arbor Street. Note this will require a super majority vote (5/7) for the fund balance transfer.

Summary Report:
Staff received quotes for the crosswalk improvement project on July 29, 2016. Numerous contractors were solicited for the work and the City received three quotations for the work. The quotes also had a deduct alternate to remove the bumpout if funding for the project didn't allow.

This item is back before council due to costs coming in over the project budget. The project can still move forward with the original approved budget, however, the bumpout and rectangular rapid flashing beacon need to be removed to keep the project in line with the authorized funding.

The approved project funding is $124,000 with the City share $104,000 and the School District share $20,000. At the July 5 Council meeting additional funding was not set aside for the addition of the bumpout as it was hopeful the bids would allow for it. Staff had a project contingency of 20% beyond the normal 10% to try to offset variability in the quotes with the tight construction timeline. However, bids still came in over the project budget.

A summary of the authorized funding and bid cost is shown in the table below. To fund the project with the bumpout and RRFB an additional $37,600 is needed.

Construction
$86,000
$117,361

Bumpout

$10,563

Total Construction
$86,000
$127,924

Contingency (20%)
$17,200
$12,800 (10%)

Overhead (20%)
$20,640
$20,640

Total Project
$123,840
$161,440
($37,600)


Alternative Options:

a. The RRFB could be removed from the project - it w...