File #: 22-012    Version: 1 Name:
Type: Information/Discussion Item Status: Agenda Ready
File created: 12/16/2021 In control: City Council
On agenda: 1/4/2022 Final action:
Title: Update/Discussion on Rice County 10-Year Transportation Improvement Plan.
Attachments: 1. 1 - Ten Yr TIP Nov 2021 11x17_final, 2. 2 - 1-11-22 TIP Funding, 3. 3 - Planned Walking & Biking Network Map, 4. 4 - 2022-2026 CIP 24x36
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Meeting Date:                     January 4, 2022

 

To:                                          Mayor and City Council

                                          City Administrator

 

From:                                          David E. Bennett, Public Works Director/City Engineer

 

Title

Update/Discussion on Rice County 10-Year Transportation Improvement Plan.

 

Body

Action Requested:                     

The Northfield City Council discusses the Rice County 10-Year Transportation Improvement Plan.

 

Summary Report:

On November 23, 2021 Rice County Engineer presented to the County Board the 2022-2031 Transportation Improvements plan.  The County Engineer has indicated that the first 5-years of the plan are in more of the scoping/design process.  Beyond the first 5-years the plan is more conceptual and subject to adjustments.  A public hearing on the plan is scheduled for January 11, 2022.

 

A couple of items to highlight in the plan as it relates to the City:

 

                     2024 County Road 79/Wall Street - Reconstruction/Bridge Replacement

o                     This will have some work beginning in 2022.  The City and County will have a cooperative agreement, and start project scoping and Right-of-Way needs.

o                     2023 Final Design

o                     2024 Construction

                     2024 County Road 78 - Bridge Replacement

                     2026 CSAH 28 (Jefferson Parkway to East to County Road 42)

o                     Staff believes the overlay should come further east to Prairie Street and include the trail overlay.

o                     This currently is not in the City 5-year CIP as it is currently proposed as outside City Limits.

                     2030 County Road 78/Armstrong Road - Currently identified as a Reclaim

                     2031 County Road 43 (Lincoln Street to Dakota County Line) - Reconstruct

 

Also attached for reference is the City Planned Walking and Biking network map along with the 5-year CIP Map for the City.

 

Any specific thoughts/comments from Council on the plan will be shared with Rice County.

 

Alternative Options:

Financial Impacts:                     

Tentative Timelines:                     

Public Hearing is January 11, 2022 @ 9:00 a.m.