File #: 21-474    Version: 1 Name:
Type: Information/Discussion Item Status: Agenda Ready
File created: 7/26/2021 In control: City Council
On agenda: 8/17/2021 Final action:
Title: City Council discussion on the 2022 NW Area Mill and Overlay Project Feasibility Report.
Attachments: 1. 1 - 2022 NW Area Mill and Overlay Project, 2. 2 - Bikeway Concepts, 3. 3 - Sidewalk/Trail Concepts, 4. 4 - Cannon Valley Drive/North Avenue Crosswalk Concepts, 5. 5 - Transit Hub/Depot Pedestrian Routes, 6. 6 - Public Feedback, 7. 7 - Project Process, 8. 8 - Presentation 2022 NW Area Mill and Overlay Project, 9. 9 - Planned Walking & Biking Network Map, 10. 10 - Hyperlink - Draft Feasibility Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Meeting Date: August 17, 2021

To: Mayor and City Council
City Administrator

From: Sean Simonson, Engineering Manager
David Bennett, Public Works Director/City Engineer

Title
City Council discussion on the 2022 NW Area Mill and Overlay Project Feasibility Report.

Body
Action Requested:
The City of Northfield discusses the 2022 NW Area Mill and Overlay Project

Summary Report:
City Council Ordered the Preparation of Feasibility Report for the NW Area Mill and Overlay Project at the May 4, 2021 City Council meeting, which includes the following Street Segments: (Attachment 1)

* Thye Parkway from Lockwood Drive to Eveleth Avenue
* Lockwood Drive from Gill Lane to Thye Parkway
* Quie Lane from Lockwood Drive 650' west
* Rolvaag Court
* Lupine Drive from Eveleth Avenue to Cannon Valley Drive
* Lupine Court
* Cannon Valley Drive from North Avenue 1450' north
* Woodland Trail
* Greenleaf Court
* Wildwood Court
* North Avenue from Eveleth Avenue to Summerfield Drive
* Juniper Avenue from Lincoln Street to Lincoln Parkway
* Joann Court
* Headley Court
* St. Olaf Avenue from Lincoln Street to TH 3
In addition to the Street Segments listed above, Staff referenced the Northfield Pedestrian, Bike, and Trail System Plan for any proposed Sidewalk, On-Street Bikeways, or Off-Street Trail/Path recommended in the plan. Staff will be including the following Walking and Biking/Pedestrian Improvements segments in the Feasibility Report, which are in close proximity to the proposed Project: (Attachment 1)
1. St. Olaf Avenue On-Street Bikeway (Attachment 2)
2. Lockwood Drive On-Street Bikeway (Attachment 2)
3. Thye Parkway On-Street Bikeway (Attachment 2)
4. Forest Avenue On-Street Bikeway (Attachment 2)
4. North Avenue Trail/Sidewalk/Bikeway (Attachment 2)
5. Liberty Park Connecting Trail (Attachment 3)
6. Highland Avenue/Ivanhoe Drive Sidewalk (Attachment 3)
7. Greenvale Avenue Sidewalk (Attachment 3)