File #: 21-350    Version: 1 Name:
Type: Motion Status: Passed
File created: 6/4/2021 In control: City Council
On agenda: 6/15/2021 Final action:
Title: Consider Motion Adopting Wastewater Treatment Plant's Facility Plan Update.
Attachments: 1. 1 - Final WWTP Facility Plan Update
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Meeting Date:                      June 15, 2021

 

To:                                          Mayor and City Council

                                          City Administrator

 

From:                                          Justin Wagner, Utilities Manager

                                          David Bennett, P.E., Public Works Director/City Engineer

 

Title

Consider Motion Adopting Wastewater Treatment Plant’s Facility Plan Update.

 

Body

Action Requested:                     

The Northfield City Council considers a Motion adopting the Wastewater Treatment Plant’s Facility Plan Update.

 

Summary Report:

On August 5, 2019, the City of Northfield hired Jacobs Engineering Group (Jacobs) to provide the following services as part of the contract:

 

1)                     Phase 1 - Operations Assessment, previously presented to Council and included in appendix

2)                     Phase 2 - Condition Assessment - previously presented to Council and included in appendix

3)                     Phase 3 - Facility Plan (Attachment 1) - consider motion approving tonight to Council

 

Tonight’s request is to consider adopting the Wastewater Treatment Plant’s Facility Plan Update. This was discussed at the June 8, 2021 City Council work session. As part of the Facility Plan, Jacobs Engineering Group updated the Wastewater Treatment Plant’s Facility Plan from 2016. The objectives of this Facility Study update included:

1)                     Review and update projected flows and loads to 2040.

2)                     Review the 2016 Facility Plan improvements, document the updated status of improvements that have already been completed, and identify additional improvement alternatives that were uncovered as part of the Operational Assessment and Condition Assessment. Provide updated cost estimates for updates and revisions that are identified.

3)                     Review the 2016 Facility Plan project costs and provide updated cost summaries based on the status of improvements that are already completed and the updates and revisions identified for this Facility Plan Update.

 

As part of the flows and loads projections through 2040, the following plant influent load projections were identified in Table 2-5 of the Facility Plan Update which is listed below.

 

Table 2-5. Design Capacity and Projected Flows and Loads

Item

Original/Permitted Design Basisa

Updated Design Basisb

2025

2030

2035

2040

Population

 

 

23,228

24,174

25,155

26,177

AWW Flow (mgd)

5.2

5.2

3.25

3.38

3.51

3.65

CBOD5 - Average Day (lb/d)

6,200

7,440

5,881

6,010

6,145

6,285

CBOD5 - Max Month (lb/d)

7,999

9,239

7,504

7,657

7,817

7,984

TSS - Average Day (lb/d)

5,001

6,001

5,855

6,040

6,240

6,444

TSS - Max Month (lb/d)

6,400

7,400

8,817

9,118

9,432

9,758

a From Wastewater Treatment Facilities Improvements contract drawings (Bolton & Menk, Inc., 1999) and Northfield Wastewater Treatment Facility NPDES permit issued June 1, 2020  b From 2005 letter attachment to Wastewater Treatment Facility Plan (Bolton & Menk, Inc., 2016)

 

Based upon the level of TSS above the Updated Design Basis, Jacobs along with Kruger (now Veolia) completed a further review of the loading capacity of the Wastewater Treatment Plant. The Veolia team indicated that because Northfield’s installation was one of the first of its kind, the design tools used for sizing were more conservative than the design tools used today for sizing new BAF plants.  Veolia offered to review the Northfield performance data and model the plant’s performance using their latest process design tools.  Their results confirmed the existing 10 cell BAF process can handle the future flow and load cases through 2040 easily with 10 cells in service and can even handle more flow or higher strength wastewater.  Based on Veolia’s recommendation the City will be able to handle an influent load between 10,000 and 17,500 pounds per day of Total Suspended Solids. This indicated the City will have the ability to handle the influent load for TSS past 2040 projections.

The Facility Plan Updated costs to all projects from the 2016 Facility Plan and identified additional projects to be completed at the WWTP. Table 4-2 of the Facility Plan lays out the implementation plan with the project costs based on 2021 dollars for a total of $14,694,356. When staff develops the Capital Improvement Plan, staff will allocate inflation costs for the projects. Staff is working with Baker Tilly to update the Rate Study that was completed in 2018 to determine if the current rate adjustments are adequate for funding the projects.

Table 4-2. Implementation and Spending Schedule

Item

2022-2025

2026-2030

Liquid Sludge Storage

$3,820,313

 

Biosolids Cake Storage

 

$3,945,875

Influent Lift Pumps

$720,000

 

Preliminary Treatment

 

$300,000

Primary Clarification

$354,000

 

Process Lift Pumps

 

$210,000

BAF Blower Replacement

$1,901,600

 

Control System and Card Access System Upgrades

$864,000

 

HVAC Equipment Replacement

$215,568

 

Water Supply System

 

$1,000,000

Roof Replacement

$763,000

 

Standby Generator

 

$600,000

Total

$8,638,481

$6,055,875

 

 

Tentative Timelines:                     

Consideration of the final Wastewater Treatment Plant Facility Plan tonight.