File #: 19-828    Version: 1 Name:
Type: Information/Discussion Item Status: Agenda Ready
File created: 3/19/2019 In control: City Council
On agenda: 4/16/2019 Final action:
Title: Discussion of Transit Hub and Depot Projects.
Attachments: 1. 1- 6-29-17 Draft NF140077 Historic Depot and Transit Hub Plans, 2. 2- 2018 Annual Report-FINAL, 3. 3 - HF 2295 Northfield Regional Transi Hub Capital Investment Committee Handouts 03_19_2019
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Meeting Date:                     April 16, 2019

 

To:                                          Mayor and City Council

                                          

From:                                          Ben Martig, City Administrator

 

 

Title

Discussion of Transit Hub and Depot Projects.

 

Body

Action Requested:                     

Discussion only.

 

Summary Report:

Representatives of the Save the Northfield Depot will give a presentation of their 2018 Annual Report.

 

After completion of the Save the Northfield Depot presentation, Staff will provide an update on the potential transit hub project after the presentation. As you know, we have pursuing $2,500,000 for a potential project.  See the attachment for more information.

 

The City Council had discussed potentially exploring the construction of the access road independent of other funding in an effort to incrementally pursue the transit hub by at least getting a transfer area established as well as to benefit the Save the Northfield group to assist in completing their project.  Should the Council be interested in pursuing assistance to complete an access road in 2019, we would need to prepare in the near future to work out details of bidding and agreements with the Save the Northfield Depot group.

 

Staff will be preparing more information in advance of the meeting including a presentation on the issue.

 

Alternative Options:

Discussion only.

 

Financial Impacts:                     

Staff is working on cost estimate at this time but believes the access road project would cost around $300,000.

 

Tentative Timelines:                     

If Council wishes to pursue construction of the access drive in 2019, this is what the schedule would look like.

 

                     May 7, 2019 City Council - Consider Approve Plans and Authorize Bidding

                     May 7, 2019 City Council - Agreements with Save the Northfield Depot

                     June 6, 2019 Open Bids

                     June 18, 2019 Award

                     July - August Construction