File #: 19-796    Version: 1 Name:
Type: Motion Status: Passed
File created: 3/14/2019 In control: City Council
On agenda: 4/2/2019 Final action:
Title: Consider Approving Professional Service Agreement for TH 246 and Jefferson Parkway Roundabout Improvement Project.
Attachments: 1. 1 - Consultant-professional services contract_SEH, 2. 2 - TH 246 & Jefferson Parkway RFP, 3. 3 - SEH - TH 246 & Jefferson Parkway Roundabout Proposal, 4. 4 - Bolton & Menk TH 246 & Jefferson Parkway Roundabout Proposal, 5. 5 - Stantec - TH 246 & Jefferson Parkway Roundabout Proposal
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Meeting Date: April 2, 2019

                                                                

To:                        Mayor and City Council

                     City Administrator

                     

From:  Sean M. Simonson, Engineering Manager

David E. Bennett, P.E., Public Works Director/City Engineer

Mitzi Baker, Community Development Director

 

Subject: 

TITLE

Consider Approving Professional Service Agreement for TH 246 and Jefferson Parkway Roundabout Improvement Project.

BODY

Action Requested:                     

The Northfield City Council approves a Motion for a professional service agreement (Attachment 1) with Short Elliot and Hendrickson (SEH) for City Project (STRT2019-A43) TH 246 and Jefferson Parkway Roundabout Improvement Project in the amount of $395,926.

 

Summary Report:

At the February 12, 2019 City Council meeting, a motion was passed to seek proposals (Attachment 2) for professional engineering services for the TH 246 and Jefferson Parkway Roundabout Improvement Project.  The proposals were evaluated based on each firm’s price, experience with similar projects, project personnel, and ability to deliver a project with the scope below:

 

                     Pedestrian and Gateway Improvements

                     Street and Utility Design

                     Construction Services

                     Geotechnical Testing

                     Surveying

 

Staff reviewed the proposals and is recommending SEH be retained for professional services.  SEH’s proposal demonstrated their extensive background in delivering projects of similar scope to the TH 246 and Jefferson Parkway Roundabout Improvement Project.  SEH has also contracted with the City in the past and has been successful at delivering projects for the City of Northfield.  Staff received proposals from the following consultants:

 

1.                     SEH Inc. - $395,926 (Attachment 3)

2.                     Bolton and Menk - $479,764 (Attachment 4)

3.                     Stantec - $658,444 (Attachment 5)

 

Alternative Options:

The Council could decide not to enter into a contract with an engineering firm for this project; however, this may delay the project, and possibly jeopardize grant dollars already awarded from MnDOT for this project.

 

Financial Impacts:                     

The City of Northfield has already secured a total of $1,383,480 in grants from MnDOT’s Local Partnership Program (LPP) and MnDOT’s Local Road Improvement Program (LRIP) for this project. 

 

Tentative Timelines:                     

Staff will develop a Project Process with the successful consultant once the Engineering Contract is approved.