File #: 19-727    Version: 1 Name:
Type: Information/Discussion Item Status: Agenda Ready
File created: 1/3/2019 In control: City Council
On agenda: 2/19/2019 Final action:
Title: Update on Northfield Hospital Clinic and Birthing Unit Expansion.
Attachments: 1. 1 - Presentation Birth Center & Clinic Expansion Project Update, 2. 2 - Hospital Update - SADMIN_KONI19021408280, 3. 3- Hosp Resolution Approving Concept, 4. 4 - Northfield Comprehensive Plan Facilities - see highlighted
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Meeting Date:                     February 19, 2019

 

To:                                          Mayor and City Council

                                          

 

From:                                          Ben Martig, City Administrator

 

Title

Update on Northfield Hospital Clinic and Birthing Unit Expansion.

 

Body

Action Requested:                    

The Northfield City Council will receive a presentation on the Northfield Hospital & Clinics Expansion Project.

 

Summary Report:

Northfield Hospital President Steve Underdahl and Chief Operating Officer Jerry Ehn will be in attendance again to give an update to the City Council on the status of the clinic and birthing unit expansion.

 

The City Council had approved the concept for the clinic and birth center expansion at the meeting on December 11, 2018.  The resolution authorizing included language that delegated the authority to the Northfield Hospital and Clinic to “select such professional services as necessary to design and manage the construction of the project.” The professional service has been completed and the next phase to begin designs will be starting soon. 

 

Please see attached presentation and other background materials to this memo.

 

Staff also added some information related to the City Comprehensive Plan and community facilities for reference as well.

 

Alternative Options:

None recommended.

 

Financial Impacts:                    

Not in this update.

 

Tentative Timelines:

ü                     December - January 2018 - Hospital Select Contractor/Architect

February 19 - Update to City Council

March/April - Update to City Council

April/May - NH+C Presentation to City Council the final project design, plans and specifications

June - City Council approve construction contracts