File #: 18-559    Version: 1 Name:
Type: Motion Status: Passed
File created: 10/31/2018 In control: City Council
On agenda: 11/13/2018 Final action:
Title: Consider Approval of Northfield Community Resource Center Senior Center Roof Repair Project Change Order No. 1 and Final Payment for Project FACL 2017-M10.
Attachments: 1. 1 - Change Order 1, 2. 2 - Final Payment
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Meeting Date:                     November 13, 2018

 

To:                                          Mayor and City Council

                                          City Administrator

 

From:                                          Todd Fredrickson, Facilities Manager                     

 

Title

Consider Approval of Northfield Community Resource Center Senior Center Roof Repair Project Change Order No. 1 and Final Payment for Project FACL 2017-M10.

 

Body

Action Requested:                     

The Northfield City Council considers a Motion to approve the NCRC Senior Center Roof Repair Project Change Order No. 1 and Final Payment for Project FACL 2017-M10.

 

Summary Report:

Original specifications for the roof replacement included a small allowance for plywood sheathing replacement.  After tearing off the old shingles, it was determined that a significant amount of plywood sheathing needed to be replaced.  Roof louvers were determined to be a better option than the original ridge venting.  Structural repairs were necessary to support the roof trusses over the pool area.  Staff agrees with the change order and recommends that it be approved and along with the final payment.

 

Alternative Options:

N/A

 

Financial Impacts:                     

Original Construction Contract                     $132,800

Change Order 1                                                                $24,976.60

Final Contract Amount                                          $157,776.60

 

The overall project is within the total Project Budget of $180,000.

 

Tentative Timelines:                     

N/A