City Council Meeting Date: August 20, 2019
To: Mayor and City Council
City Administrator
From: Sean Simonson, Engineering Manager
David Bennett, Public Works Director/City Engineer
Title
Consideration of Resolution Ordering Preparation of Feasibility Report for the 2020 Mill and Overlay Project.
Body
Action Requested:
The Northfield City Council approves the attached Resolution ordering the preparation of a feasibility report for the 2020 Mill and Overlay Project (STRT2020-A45) and to assess benefited properties for all or a portion of the cost of the improvement.
Summary Report:
The approval of the attached resolution (Attachment 1) is the initial step in moving the 2020 Mill and Overlay Project (STRT2020-A45) forward. By this resolution, the City Council orders the preparation of a feasibility report, which is a necessary step under Chapter 429 of the Minnesota Statutes. Chapter 429 clearly specifies the actions that must be taken to assess property owners for the cost of local improvements. See Attachment 2 for a detailed project process.
The proposed scope of the 2020 Mill and Overlay Project includes the following streets: (Attachment 3)
1. First Street - College Street to Maple Street
2. Second Street - Washington Street to Oak Street
3. Third Street - Washington Street to Oak Street
4. Fourth Street - Nevada Street to Prairie Street
5. Union Street - First Street to Second Street
6. College Street - First Street to Third Street
7. Winona Street - First Street to Fourth Street
8. Nevada Street - First Street to Fourth Street
9. Maple Street - First Street to Fourth Street
10. Elm Street - Second Street to Fifth Street
11. Oak Street - Second Street to Fourth Street
12. Heritage Drive - TH 3 to Hidden Valley Apartments
13. Jefferson Road - Hidden Valley Road to Heritage Drive
14. Seventh Street - Water Street to West dead end
15. Eight Street - Water Street to Linden Street
The streets listed above are currently in the 2020 - 2024 proposed C...
Click here for full text