City Council Meeting Date: September 7, 2021
To: Mayor and City Council
City Administrator
From: Sean Simonson, Engineering Manager
David E. Bennett, PE - Public Works Director/City Engineer
Subject:
TITLE
Consider Accepting Feasibility Report and Authorizing Plans and Specifications for the 2022 NW Area Mill and Overlay Project (STRT2022-A59).
BODY
Action Requested:
The Northfield City Council approves the attached Resolution accepting the feasibility report and Authorize Preparation of Plans and Specifications for the 2022 NW Area Mill and Overlay Project (STRT2022-A59).
Summary Report:
The feasibility report has been completed and finds that the 2022 NW Area Mill and Overlay Project is necessary, feasible and cost effective. A link to the Feasibility Report is below:
https://www.ci.northfield.mn.us/1445/2022-NW-Area-Mill-and-Overlay-Project
(See Attachment 2 for clickable link)
At the May 4, 2021 City Council meeting, the City Council passed Council Resolution 2021-043 which ordered the preparation of a feasibility report for this project. The proposed scope of the Mill and Overlay Project includes the following streets:
* Thye Parkway from Lockwood Drive to Eveleth Avenue
* Lockwood Drive from Gill Lane to Thye Parkway
* Quie Lane from Lockwood Drive 650' west
* Rolvaag Court
* Lupine Drive from Eveleth Avenue to Cannon Valley Drive
* Lupine Court
* Cannon Valley Drive from North Avenue 1450' north
* Woodland Trail
* Greenleaf Court
* Wildwood Court
* North Avenue from Eveleth Avenue to Summerfield Drive
* Juniper Avenue from Lincoln Street to Lincoln Parkway
* Joann Court
* Headley Court
* St. Olaf Avenue from Lincoln Street to TH 3
* Forest Avenue from Lincoln Street to Odd Fellows Campus
In addition to the Street Segments listed above, Staff referenced the Northfield Pedestrian, Bike, and Trail System Plan for any proposed Sidewalk, On-Street Bikeways, or Off-Street Trail/Path recommended in the plan. St...
Click here for full text