City Council Meeting Date:                     January 15, 2019

 

To:                                          Mayor and City Council

                                          City Administrator

 

From:                                          Nate Carlson, Economic Development Coordinator

                                          Mitzi Baker, Community Development Director

                                          Scott Tempel, City Planner

 

Title

Lot 5 Extension Request Discussion

 

Body

Action Requested:                     

No action at this time.

 

Summary Report:

The City of Northfield executed a contract for private development with Big Ten Residential, LLC on May 17, 2016 for the development of the Crossings Site. The developer requested acquisition of the city-owned “Lot 5” property as part of the development agreement. “Lot 5” is on the Northeast corner of the State Highway 3 and 2nd Street West intersection.

 

Section 4.3 of the Contract for Development states that Future Commercial Improvements on Lot 5 must commence on or before December 31, 2018 and be completed on or before December 31, 2019. The Developer enters into default of the agreement if this action does not happen, and the City acquires the land from the developer.

 

The Developer, now known as Rebound Development Partners, LLC, has requested an extension for the commencement of future commercial improvements on Lot 5. The letter request for extension is attached to this report. At this time, the developer is requesting a two-year extension. However, the Council has not had the opportunity to discuss further options related to the possible extension. The Council approved a three-month extension of the deadline rather than a two-year extension in order to allow the opportunity for City Council to discuss the appropriate extension duration, and the Council’s options should the developer default on the contract.

 

The three-month extension changed the Future Commercial Improvements commencement date to March 31, 2019 and the completion date to March 31, 2020. The Developer is submitting a request for a two-year extension following the initial three-month extension.

 

The Developer has also proposed that after the two-year extension that the developer requests an additional two-year extension while also providing the City with $20,000.

 

Representatives from Rebound, Brett Reese, Scott Koester, and Chris Kennelly, will be presenting their proposal to Council at the work session. Following the work session and consensus, staff intends to draft language for the second amendment to the Contract for Private Development.

 

Alternative Options:

 

 

Financial Impacts:                     

Should the City Council take no action to approve a deadline extension, the City of Northfield will acquire ownership of the Lot 5 property from the developer at no cost.

 

If the Developer fails to meet the two-year extension deadline, the City would receive $20,000 for a second extension for two-years.

 

Tentative Timelines:                     

                     Council Discussion and Feedback on Proposal - January 15 worksession.

                     Council consider extension for Lot 5 improvements: January 22, 2019

                     Certificate of Commencement for Lot 5 improvements: March 31, 2021

                     Certificate of Completion for Lot 5 improvements: March 31, 2022