File #: 17-727    Version: 1 Name:
Type: Motion Status: Passed
File created: 3/17/2017 In control: City Council
On agenda: 3/21/2017 Final action:
Title: Consider Approval of AIA Document B132 - 2009 Standard Form of Agreement Between Owner and Archiect, Construction Manager as Adviser Edition with DJ Medin Architects.
Attachments: 1. AIA Document B132 - 2009, 2. NAFRS Facility Upgrade Schedule - REVISED 3-10-17
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Meeting Date:                     March 21, 2017

 

To:                                          Mayor and City Council

 

From:                                          Ben Martig, City Administrator

 

Title

Consider Approval of AIA Document B132 - 2009 Standard Form of Agreement Between Owner and Archiect, Construction Manager as Adviser Edition with DJ Medin Architects.

 

Body

Action Requested:                     

The Northfield City Council approves AIA Document B132 - 2009 Standard Form of Agreement Between Owner and Archiect, Construction Manager as Adviser Edition with DJ Medin Architects.

 

Summary Report:

The proposed architect agreement was presented to the City Council at the worksession on March 14, 2017.  The contract is for architectural services for design of the NAFRS expansion project as well as bidding and construction phase services.  Details are included in the agreement.  City Attorney Chris Hood, Kennedy & Graven Bond Counsel Jenny Boulton, Kennedy & Graven Attorney Jim Strommen advising on contract management have all participated in the development of the amended standard agreement along with City staff and NAFRS representatives.

 

The NAFRS Board unanimously recommended Council approval of this agreement with DJ Medin at their regular board meeting on Thursday, March 16.

 

Alternative Options:

Remove from consent agenda for further discussion or clarification.

 

Financial Impacts:                     

Total costs of the “basic services” under Section 11.5 are $161,500.  Other details of the fees are provided in Article 11. Compensation of the attached agreement.

 

Tentative Timelines:                     

Please see attached current draft project schedule.