City of Northfield MN
File #: Res. 2023-093    Version: 1 Name:
Type: Resolution Status: Passed
File created: 7/27/2023 In control: City Council
On agenda: 10/3/2023 Final action: 10/3/2023
Title: Consider Accepting Feasibility Report and Authorizing Plans and Specifications for the 2024 Jefferson Parkway West Mill and Overlay and Mill Towns Trail Improvements Project (STRT2024-A78).
Attachments: 1. 1 - 2024 Jefferson Parkway West Mill and Overlay and Pedestrian Improvements Project Resolution, 2. 2 - Hyperlink to Feasibility Report, 3. 3 - Project Location Map, 4. 4 - Project Process, 5. 5 - Bolton & Menk Presentation Link, 6. 6 - Jefferson Pkwy M&O and MTT Improvements_Feasibility Presentation, 7. 7 - SUPPLEMENTAL 1 - Background Memo, 8. 8 - SUPPLEMENTAL 1 - Spruce Court Trail and Sidewalk Improvement Service Area
City Council Meeting Date: October 3, 2023

To: Mayor and City Council
City Administrator

From: Sean Simonson, Engineering Manager
David E. Bennett, PE - Public Works Director/City Engineer

Subject:
TITLE
Consider Accepting Feasibility Report and Authorizing Plans and Specifications for the 2024 Jefferson Parkway West Mill and Overlay and Mill Towns Trail Improvements Project (STRT2024-A78).

BODY
Action Requested:
The Northfield City Council approves the attached Resolution Accepting Feasibility Report and Authorizing Plans and Specifications for the 2024 Jefferson Parkway West Mill and Overlay and Mill Towns Trail Improvements Project (STRT2024-A78).

Summary Report:
A recorded PowerPoint presentation is attached. There will be no formal presentation at the City Council Meeting.

The feasibility report has been completed and finds that the Jefferson Parkway West Mill and Overlay and Mill Towns Trail Improvements Project is necessary, feasible and cost effective. A link to the Feasibility Report is below:

https://www.northfieldmn.gov/1598/Jefferson-Parkway-West-Mill-Overlay-and-
(See Attachment 2 for clickable link)

City Council Ordered the Preparation of Feasibility Report for the Jefferson Parkway West Mill and Overlay and Mill Towns Trail Improvements Project Feasibility Report at the May 16, 2023 City Council meeting, which includes the following Street Segments (Attachment 3):

* Jefferson Parkway from TH 3 to TH 246 (Mill and Overlay & Mini Roundabout Installation)

In addition to the Street Segments listed above, Staff referenced the approved Northfield Pedestrian, Bike, and Trail System Plan and the approved Pedestrian and Bicycle Analyzation Report for any proposed Sidewalk, On-Street Bikeways, Crossing Improvements, or Off-Street Trail/Path recommended in the plans. Staff will be including the following Walking and Biking/Pedestrian/Crossing Improvements in the Feasibility Report:

* TH 3 from Riverside...

Click here for full text