Legislation Details

File #: 26-361    Version: 1 Name:
Type: Motion Status: Consent Agenda
File created: 5/8/2026 In control: City Council
On agenda: 7/7/2026 Final action:
Title: Consideration of Approval of Professional Services Contract with Bolton and Menk, Inc. for the Wastewater Treatment Plant Pretreatment, Primary and Generator Project.
Attachments: 1. 1 - Bolton and Menk CSC 2026 WWTP Improvements, 2. 2 - Bolton and Menk Proposal
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
City Council Meeting Date: July 7, 2026

To: Mayor and Members of Council
City Administrator

From: Justin Wagner, Utilities Manager
David Bennett, P.E., Public Works Director/City Engineer

Title
Consideration of Approval of Professional Services Contract with Bolton and Menk, Inc. for the Wastewater Treatment Plant Pretreatment, Primary and Generator Project.

Body
Action Requested:
The Northfield City Council considers a Motion approving the professional services contract with Bolton and Menk, Inc. for the Wastewater Treatment Plant Pretreatment, Primary and Generator Project.

Summary Report:
The City Council is being asked to approve the professional services contract with Bolton and Menk, Inc. for the Wastewater Treatment Plant Pretreatment, Primary and Generator Project (WSTR2026-J41).

The City requested professional consultant services related to equipment replacements at the wastewater treatment plant that were identified in the 2021 Facility Study Update. The City received one proposal while requesting from Bolton and Menk, Inc. and SEH, Inc. Bolton and Menk, Inc.'s proposal was at $329,890.00 was 12.7% of the estimated project costs which is typical for design and construction services.

The planned project is to replace all of the pretreatment equipment including fine screens, and grit separator, primary process pumps including variable frequency drives and piping and replacement of the backup generator. All of these items are from the plant upgrade from 1999-2001. This project is planned to be designed in 2026 and constructed in 2027 and 2028 depending on lead times of equipment.

City Plans & Policies Relevance:
2021 Facility Plan Update

Alternative Options:
Not recommended

Financial Impacts:
The professional service contract is $329,890.
The estimated project cost is $2,594,621 prior to design services.

Tentative Timelines:
Project Design - July through December 2026
Approval of Plans and Specifications and Advertisement for Bid ...

Click here for full text