File #: 18-406    Version: 1 Name:
Type: Motion Status: Passed
File created: 6/26/2018 In control: City Council
On agenda: 8/21/2018 Final action: 8/21/2018
Title: Consider Approval of Additional Professional Services with Short Elliot Hendrickson Inc. (S.E.H.) for Division Street and Seventh Street Reconstruction, Washington Street Mill and Overlay, and Various Parking Lot Rehabilitations Project and Spring Creek Road.
Attachments: 1. 1- SIGNED SEH CONTRACT, 2. 2- Additional Services Letter 08 08 18
City Council Meeting Date: August 21, 2018

To: Mayor and City Council
City Administrator

From: Sean Simonson, Engineering Manager
David E. Bennett, P.E. Public Works Director/City Engineer

Subject:
TITLE
Consider Approval of Additional Professional Services with Short Elliot Hendrickson Inc. (S.E.H.) for Division Street and Seventh Street Reconstruction, Washington Street Mill and Overlay, and Various Parking Lot Rehabilitations Project and Spring Creek Road.

BODY
Action Requested:
The Northfield City Council Considers a Motion to amend the compensation amount with S.E.H for the additional services on the Division Street Project (2018STRT A37) and Spring Creek Road Project (2018STRT A38) from $366,892 to $778,501.

Summary Report:
At the August 22, 2017 Council Meeting, City Council approved a contract with S.E.H for design and construction services related to the above stated projects. In order to facilitate the timeline of the projects, the City's proposal for requesting professional services were retained with the understanding that the City was working through the engagement and Complete Street Conceptual Design with Toole Design Group for Division and Seventh Street.

Therefore, at the time of entering into the contract for Division and Washington Street, the full scope of the Complete Streets features such as parking bumpouts, valley gutters, and raised intersections were not identified. These items, along with a variance process for State-Aid, increased the costs related to the design and construction. The original proposal had Division Street and Washington Street costs at $172,405. The request for the additional services is for an additional $194,600 for a total professional services cost of $367,005. This cost is more reflective of what is typically seen for professional service costs. This is roughly 10% of the construction cost for these services, project professional services typically range between 1...