City Council Meeting Date: October 3, 2023
To: Mayor and City Council
City Administrator
From: Sean Simonson, Engineering Manager
David E. Bennett, PE - Public Works Director/City Engineer
Subject:
TITLE
Consider Accepting Feasibility Report and Authorizing Plans and Specifications for the 2024 College Street and Water Street Areas Reconstruction Project (STRT2024-A77).
BODY
Action Requested:
The Northfield City Council approves the attached Resolution Accepting Feasibility Report and Authorizing Plans and Specifications for the 2024 College Street and Water Street Areas Reconstruction Project (STRT2024-A77).
Summary Report:
A recorded PowerPoint presentation is attached. There will be no formal presentation at the City Council Meeting.
The feasibility report has been completed and finds that the 2024 College Street and Water Street Areas Reconstruction Project is necessary, feasible and cost effective. A link to the Feasibility Report is below:
https://www.northfieldmn.gov/1597/College-Street-Water-Street-Areas-Recons
(See Attachment 2 for clickable link)
At the May 16, 2023 City Council meeting, the City Council passed Council Resolution 2023-046 which ordered the preparation of a feasibility report for this project. The proposed scope of the Project at that time included the following improvements: (Attachment 3)
* College Street from Woodley Street to Seventh Street (Street Reconstruction)
* Winona Street from Woodley Street to Seventh Street (Street Reconstruction)
* Ninth Street from College Street to Winona Street (Street Reconstruction)
* Eighth Street from College Street to Nevada Street (Street Reconstruction)
* Water Street from Linden Place to Woodley Street (Street Reconstruction)
* Sumner Street from Water Street to Division Street (Street Reconstruction)
* Fremont Street from Water Street to Division Street (Street Reconstruction)
* Spruce Court to Linden Place (Utility Improvements)
In additio...