City Council Meeting Date: October 7, 2025
To: Mayor and City Council
City Administrator
From: Justin Wagner, Utilities Manager
Title
Consider Motion Approving Permanent and Temporary Construction and Utilities Easements with Mark J. Pritchard and Julie A. Pritchard Joint Revocable Trust for Jefferson Parkway Extension, Sandstone Street Construction and Utility Improvements Project.
Body
Action Requested:
The Northfield City Council approves Permanent and Temporary Construction Easement Agreement with the following properties:
PID |
ADDRESS |
PROPERTY OWNER |
0805350001 |
1488 Woodley St. E. |
Mark J. & Julie A. Pritchard Trust |
0808200001 |
|
Mark J. & Julie A. Pritchard Trust |
Summary Report:
The City has designed and approved construction for the Jefferson Parkway Extension, Sandstone Street Construction and Utility Improvements Project. The project is currently in the construction phase related to the utility improvements portion of the project.
As part of the design process, the City has been working with property owners along the project for construction of a trunk sanitary sewer line that will serve both future development as well as the water treatment plant site. The City Attorney has prepared easement agreements with the above-mentioned property owners, and the property owners have approved the easements.
Alternative Options:
N/A - Staff is recommending approval of the easements for the construction project that is currently underway.
Financial Impacts:
PID |
ADDRESS |
PROPERTY OWNER |
Easement Amount |
0805350001 |
1488 Woodley St. E. |
Mark J. & Julie A. Pritchard Trust |
$15,647.50 |
0808200001 |
|
Mark J. & Julie A. Pritchard Trust |
$15,647.50 |
Tentative Timelines:
Construction is expected to begin later this fall or winter on the sanitary sewer extension.