Skip to main content
City of Northfield MN
File #: Res. 2021-094    Version: 1 Name:
Type: Resolution Status: Passed
File created: 9/22/2021 In control: City Council
On agenda: 10/5/2021 Final action:
Title: Consider Resolution Authorizing Entering into Grant Agreement with the State of Minnesota for the Northfield Transit Hub.
Attachments: 1. 1 - Resolution City Admin Grant Agreement, 2. 2 - HF 1 1st Engrossment - 91st Legislature, 2020 5th Special Session (2020 - 2020)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Meeting Date:                     October 5, 2021

 

To:                                          Mayor and City Council

                                          

From:                                          David Bennett, Public Works Director/City Engineer

 

Title

Consider Resolution Authorizing Entering into Grant Agreement with the State of Minnesota for the Northfield Transit Hub.

 

Body

Action Requested:                     

Staff recommends a motion to approve Resolution authorizing the City Administrator to enter into grant agreement with the State of MN related to General Obligation Bond Proceeds for the Northfield Transit Hub.

 

Summary Report:

In June of 2019, City Council approved a resolution requesting State of Minnesota bond funds for the Northfield Regional Transit Hub.   In the 2020 State of Minnesota legislative session, the City was successful in receiving bond funds.

The bonds funds amount to $1,750,000 for the Regional Transit Hub.  This bond includes funding for the transit hub, pavilion, railroad quiet zone improvements, and trail connections.

Once the grant agreements are approved, then the City can proceed.  The first agreement with the state will be for the design and the second agreement will be for construction.  The action today allows for the City Administrator to enter into the grant agreements.

 

Alternative Options:

NA

 

Financial Impacts:                     

The following is a current estimated total project cost as prepared:

                     

                     Table 1.  Summary total project cost for construction 2021.

                     

                     Expense

Description                                                                                    Cost (2021)

Transit Hub Building                                                                    724,000

                     Pavilion                                                                                         485,000

                     2nd Street Railroad Quiet Zone                          265,000

                     Overhead                                                                                          285,000

                     Total Project Cost                                                                 1,750,000

 

                     Revenue                     

City of Northfield Proposed                     Only necessary if 2022 bids exceed bond appropriation

                                             TIF4, Reserves, Debt

 

State of Minnesota Bond Appropriation                     $1,750,000 (100%)

Total Project Revenue                                                               $1,750,000

 

Dependent upon what happens with the bids, it is anticipated the bonds funds will cover the project cost.

 

Tentative Timelines:                     

Design Grant Agreement October 2021

Request of Proposal for Architect/Engineer Nov. - Dec 2021

Project Design Jan 2022-Jun- 2022

Construct Fall 2022

Open Transit Hub Spring/Summer 2023