Title: City Council discussion on the 2022 NW Area Mill and Overlay Project Feasibility Report.
Attachments: 1. 1 - 2022 NW Area Mill and Overlay Project, 2. 2 - Bikeway Concepts, 3. 3 - Sidewalk/Trail Concepts, 4. 4 - Cannon Valley Drive/North Avenue Crosswalk Concepts, 5. 5 - Transit Hub/Depot Pedestrian Routes, 6. 6 - Public Feedback, 7. 7 - Project Process, 8. 8 - Presentation 2022 NW Area Mill and Overlay Project, 9. 9 - Planned Walking & Biking Network Map, 10. 10 - Hyperlink - Draft Feasibility Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

City Council Meeting Date:                     August 17, 2021

 

To:                                          Mayor and City Council

                                          City Administrator

 

From:                                          Sean Simonson, Engineering Manager

                                          David Bennett, Public Works Director/City Engineer

 

Title

City Council discussion on the 2022 NW Area Mill and Overlay Project Feasibility Report.

 

Body

Action Requested:                     

The City of Northfield discusses the 2022 NW Area Mill and Overlay Project

 

Summary Report:

City Council Ordered the Preparation of Feasibility Report for the NW Area Mill and Overlay Project at the May 4, 2021 City Council meeting, which includes the following Street Segments: (Attachment 1)

 

                     Thye Parkway from Lockwood Drive to Eveleth Avenue

                     Lockwood Drive from Gill Lane to Thye Parkway

                     Quie Lane from Lockwood Drive 650’ west

                     Rolvaag Court

                     Lupine Drive from Eveleth Avenue to Cannon Valley Drive

                     Lupine Court

                     Cannon Valley Drive from North Avenue 1450’ north

                     Woodland Trail

                     Greenleaf Court

                     Wildwood Court

                     North Avenue from Eveleth Avenue to Summerfield Drive

                     Juniper Avenue from Lincoln Street to Lincoln Parkway

                     Joann Court

                     Headley Court

                     St. Olaf Avenue from Lincoln Street to TH 3

In addition to the Street Segments listed above, Staff referenced the Northfield Pedestrian, Bike, and Trail System Plan for any proposed Sidewalk, On-Street Bikeways, or Off-Street Trail/Path recommended in the plan.  Staff will be including the following Walking and Biking/Pedestrian Improvements segments in the Feasibility Report, which are in close proximity to the proposed Project: (Attachment 1)

1.                     St. Olaf Avenue On-Street Bikeway (Attachment 2)

2.                     Lockwood Drive On-Street Bikeway (Attachment 2)

3.                     Thye Parkway On-Street Bikeway (Attachment 2)

4.   Forest Avenue On-Street Bikeway (Attachment 2)

4.                     North Avenue Trail/Sidewalk/Bikeway (Attachment 2)

5.                     Liberty Park Connecting Trail (Attachment 3)

6.                     Highland Avenue/Ivanhoe Drive Sidewalk (Attachment 3)

7.                     Greenvale Avenue Sidewalk (Attachment 3)

 

When the Feasibility Report was Ordered, additional information listed below was requested by City Council to analyze in the Feasibility Report:

                     Greenvale Avenue Railroad Crossing (Attachment 3)

                     Spring Street Sidewalk (Greenvale to St. Dominic’s) (Attachment 3)

                     Cannon Valley Drive sidewalk/crossing improvement (Attachment 4)

                     Review pedestrian routes to Transit Hub/Depot (Attachment 5)

                     Highway 3 - Westside sidewalk signage

                     Intersection Evaluation of St. Olaf and TH 3 (west leg approach)

Staff held a neighborhood meeting on Wednesday July 14, 2022 to discuss the project as a whole.  At this meeting, Staff requested feedback on the options listed above, and the project as a whole. Staff also mailed out a questionnaire with the Neighborhood meeting invitation requesting feedback about the upcoming project. Attachment 6 is the feedback that was received from both the neighborhood meeting, and the questionnaires that were returned.

The purpose of this discussion item is for Staff to receive feedback from City Council on the recommended options for the following project areas:

1.                      St. Olaf Avenue Bikeway

a.                     Dedicated Bike Lanes                     

b.                     Shared Lanes

2.                     Lockwood Drive Bikeway

a.                     Shared Lanes

3.                     Thye Parkway Bikeway

a.                     One-Way Separated Bike Lanes

b.                     Buffered Bike Lanes

4.                     Forest Avenue

a.                     Shared Lanes

5.                     North Avenue

a.                     Off-Street Trail

b.                     Two-Way Separated Bike Lane (Cycle Track)

c.                     Buffered Bike Lanes

6.                     Liberty Park Connecting Trail - Future North Greenway Connection

a.                     Build/No Build

7.                     Highland Avenue/Ivanhoe Drive Sidewalk

a.                     East side of Ivanhoe Drive

b.                     West side of Ivanhoe Drive

8.                     Greenvale Avenue Sidewalk

a.                     Build/No Build

9.                     Greenvale Avenue Railroad Crossing

a.                     Build/No Build

10.                     Spring Street Sidewalk

a.                     Build/No Build

11.                     Cannon Valley Drive Sidewalk/Crossing Improvement

a.                     Build/No Build

 

Alternative Options:

Staff would be open to any additional alternatives City Council may bring forth.

 

Financial Impacts:                     

Please see the Council Presentation for the estimated costs and proposed funding for the project.

 

Tentative Timelines:                     

Staff will bring forth the Feasibility Report for approval at the September 7, 2021 City Council meeting (Attachment 7).