Skip to main content
City of Northfield MN
File #: 25-435    Version: 1 Name:
Type: Information/Discussion Item Status: Agenda Ready
File created: 7/29/2025 In control: Housing & Redevelopment Authority
On agenda: 8/7/2025 Final action:
Title: Update on 5th & Washington Redevelopment Project
Attachments: 1. 1 - City Council Resolution 2024-044, 2. 2 - EDA Resolution 2024-005, 3. 3 - Project opportunity statement, 4. 4 - Streetfront Letter of Interest, 5. 5 - Streetfront Update Memo - 2025 07 21
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

HRA Meeting Date:                     August 7, 2025

 

To:                                          Members of the Housing and Redevelopment Authority

 

From:                                          Melissa Hanson, Housing Coordinator

                                          Nate Carlson, Economic Development Coordinator                     

                                          Jake Reilly, Community Development Director

 

Title

Update on 5th & Washington Redevelopment Project

 

Body

Action Requested:                     

The update on the 5th & Washington Redevelopment Project is informational to the HRA and no action is requested at this time.

 

Summary Report:

The Northfield City Council delegated advisory authority to the Northfield EDA for downtown redevelopment projects in Resolution 2024-44 (Attached). The EDA reviewed materials and information related to potential development opportunities including constructing a more accessible and larger municipal liquor store and provided a recommended approach to the 5th and Washington Redevelopment project to Council via EDA Resolution 2024-005 (Attached).

 

Earlier this year, staff issued a request for Letters of Intent (LOI) to a select group of local developers based on a project opportunity statement that aligns with the EDA’s recommended approach (Attached). One letter of intent from a qualified developer, Streetfront Development, was received and is attached for review.

 

Streetfront prepared and provided an update to the EDA on the feasibility of the 5th & Washington Redevelopment project at the July 28 EDA meeting.

 

A desired component of the redevelopment project is housing. The housing that is currently being contemplated by the developer is homeownership; possibly a senior condo or cooperative. However, having a rental property at the site is not completely off the table. The development team will be providing a more detailed and thorough analysis of tariff, interest and labor impacts and will report their findings to the EDA October 2025.

 

Alternative Options:

N/A

 

Financial Impacts:                     

Staff time is required now. Other financial resources may need to be committed to the project in the future.

 

Tentative Timelines:                     

Financial Feasibility Review of Project - Fall 2025