Skip to main content
City of Northfield MN
File #: 18-555    Version: 1 Name:
Type: Motion Status: Passed
File created: 6/12/2018 In control: City Council
On agenda: 11/13/2018 Final action: 11/13/2018
Title: Consider Motion Approving Temporary and Permanent Easements for the 2018 Spring Creek Road Reconstruction Project.
Attachments: 1. 1 - Permanent and Temporary Easements, 2. 2 - City Council easement worksheet 11-6-18

City Council Meeting Date:                     November 13, 2018

 

To:                                          Mayor and City Council

 

From:                                          Sean Simonson, Engineering Manager

                                          Dave Bennett, City Engineer/Public Works Director

 

Title

Consider Motion Approving Temporary and Permanent Easements for the 2018 Spring Creek Road Reconstruction Project.

 

Body

Action Requested:                     

The Northfield City Council approves Permanent and Temporary Easement Agreement with the following properties:

 

P.I.D.

ADDRESS

PROPERTY OWNER

08.08.2.00.001

 

Mark Pritchard Et Al

08.05.3.50.001

 

Mark Pritchard Et Al

08.08.2.25.002

10253 Hall Avenue

Bryan F & Laurie A Grosser

08.08.2.75.001

 

Eugene & Elaine Lyman Trust

08.08.3.25.001

10511 Hall Avenue

Jeremy Baer

22.07.1.01.004

 

Sumac Properties INC

22.07.1.03.009

1705 Michigan Drive

Philip A & Megan Holleran

 

Summary Report:

City Council has moved the Spring Creek Road Reconstruction Project through the design and bidding process.  Bids were opened on September 20, 2018.  City Staff has worked with the property owners along the project corridor, and have acquired permanent and temporary easements from the above-mentioned property owners.  These temporary and permanent easements (Attachment 1) will allow the construction project to be built as previously approved by City Council.  Spring Creek Road is part of the City of Northfield’s Municipal State Aid (MSA) program.  It is recommended by the Municipal State-Aid guidelines that all temporary and permanent easements be acquired prior to awarding the construction contract.   

 

There is one property that the City is working to resolve the permanent easement with the property owner as of November 6. We are hopeful to bring the final easement forward in 2018.  Staff feels we can still proceed with the award of the project as we resolve this matter.

 

Alternative Options:

The City Council could decide not to accept these easements; however, the project contract cannot be awarded, and the project will not be able to be built as previously approved by City Council.

 

Financial Impacts:                     

A total of 11 permanent and temporary easements (Attachment 2) are required for acquisition to complete the project as approved.  City Staff consulted with the Rice County Highway Department for easement acquisition costs used for their most recent construction project on County Road 1.  Rice County paid $12,000 per acre for permanent easement acquisition, and $1,200 per acre for temporary easement acquisition.  Due to the proximity and similar land use, Staff believes it is practical to use those same acquisition costs for Spring Creek Road.  The acquisition costs are detailed in Attachment 2, a total amount of $7,249.87.

 

Tentative Timelines:                     

City Staff is anticipating awarding the construction contract at the November 20, 2018 City Council meeting.