City Council Meeting Date:  September 8, 2026

 

To:                                          Mayor and City Council

                                          City Administrator

 

From:                                          Jacob Ives, Graduate Engineer

                                          Sean Simonson, Engineering Manager

                                          David Bennett, City Engineer/Public Works Director

 

Title

Consider Approving a Grant Agreement with the Federal Highway Administration (FHWA) for the Safe Streets and Roads for All (SS4A) 2025 Planning Grant.

 

Body

Action Requested:                     

The Northfield City Council approves the grant agreement with the FHWA for the Planning Grant for Safe Streets and Roads for All.

 

Summary Report:

Staff are requesting Council approve a grant agreement with FHWA to receive $300,000 in grant funds from the USDOT and use $75,000 from the general Fund to satisfy the 20% match requirement of the grant.  The grant agreement will allow the City to develop a Safe Streets for All plan.

 

The City Adopted 2025-2028 Strategic Plan includes a strategic initiative to create a Safe Street for All Plan. Completion of the plan will help identify specific priorities for improved pedestrian safety. An Action Plan is required in order to become eligible for Federal Implementation grants.  Typically, those grants provide 80% federal funding and 20% local match.

 

 

 

Background

The USDOT is solicited project proposals to distribute $402 million to communities to prepare a Safe Streets and Roads for All Comprehensive Safety Action Plan. This plan is meant to address and prevent roadway fatalities and serious injuries. The components of a safety action plan consist of: 

 

 

                     Leadership Commitment and Goal Setting

o                     Commitment by Council to an eventual goal of zero roadway fatalities.

o                     Includes a target date for zero fatalities or a percent reduction by a certain date.

                     Planning Structure

o                     A committee, or similar body, charged with the development of the action plan.

                     Safety Analysis

o                     Analysis of existing and historical trends, crash locations and severity.

o                     Analysis includes all roadways within the city and identifies high risk locations.

                     Engagement and Collaboration

o                     Robust engagement with the public, including businesses and community groups.

o                     Engagement with other transportation agencies (townships, cities, county, state).

o                     The plan is coordinated with other city plans.

                     Policy and Process Changes

o                     Assessment of current policies, plans, guidelines, and standards.

o                     Identify opportunities to revise or develop new policies, guidelines, or standards.

                     Strategy and Project Selection

o                     Identify a set of projects and strategies that will address safety problems.

o                     Projects and strategies are prioritized in a list that provides a time range of when the countermeasures are expected to be deployed.

                     Progress and Transparency

o                     Develop a method to measure progress after the plan is developed.

o                     Develop a method to ensure transparency with the public on progress toward achieving zero roadway fatalities.

 

From 2018 - 2024 Northfield experienced 5 fatal and 14 serious injury crashes according to MnDOT crash reporting. The previous five years 2013 - 2017 experienced zero fatal and 8 serious injury crashes indicating a recent increase in crash severity. Developing a Safety Action Plan will allow the city to determine current and future crash prone locations and develop quick, low cost, and effective solutions to safety problems in these areas.

 

Once the agreement is signed staff will send a request for proposals (RFP) to engineering firms to assist city staff with the preparation of the Safety Action Plan.

 

Alternative Options:

None recommended.

 

Financial Impacts:                     

Grant Funds                      $300,000

Cash Match                     $75,000 - Funding is included in the General Fund

 

Tentative Timelines:                     

Approve Grant Agreement                      September 2026

Send RFP                                              September 2026

Project Start                                                      Winter 2026

Project Completion                                 December 2028