Title: Consideration of Authorization to Initiate a Request for Proposals (RFP) for the Wastewater Treatment Plant Improvements Project - WSTR2022-J32.
Attachments: 1. 1 - Wastewater Treatment Plant Upgrades RFP
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Meeting Date:                     January 18, 2022

 

To:                                          Mayor and City Council

                                          City Administrator

 

From:                                          Justin Wagner, Utilities Manager

                                          David Bennett, P.E., Public Works Director/City Engineer

 

Title

Consideration of Authorization to Initiate a Request for Proposals (RFP) for the Wastewater Treatment Plant Improvements Project - WSTR2022-J32.

 

Body

Action Requested:                     

The Northfield City Council considers a Motion authorizing to initiate the Request for Proposals for a Wastewater Treatment Plant Improvements Project.

 

Summary Report:

The City Council is being asked to approve the Request for Proposals (RFP) for the Wastewater Treatment Plant Improvements Project. On June 15, 2021, the City Council approved the Wastewater Treatment Plant’s Facility Plan Update. The WWTP Facility Study recommended upgrading the following items:

 

Liquid Sludge Storage

Influent Lift Pumps

Primary Clarification

BAF Blower Replacement

Control System

Card Access System Upgrades

HVAC Equipment Replacement

Roof Replacement

Rooftop solar at the WWTP

 

 

The proposed upgrades will be designed in 2022 and constructed in 2023 as laid out in the phases below.

 

Phase 1 - Design

Preparation of detailed plans and specifications shall be completed by the Consultant. All submittal applications to obtain required permits from the Minnesota Pollution Control Agency and any other required agency will be completed by the Consultant. The consultant will provide all bid documents that are required.

 

Phase 2 - Construction Phase Services

The Construction Phase Services shall also be included in the Consultant Proposal. Services including but not limited to attendance of the preconstruction meeting and ongoing site visits by the Project Engineer, to assist with plan and specification interpretation as needed during construction along with all submittal/shop drawing reviews. Construction Phase Services will also provide onsite daily inspection services, including monitoring construction activity to assure conformance to the plans and specifications, keeping a daily diary of activity, and documenting daily completion of the project, working with the Contractor and City staff to prepare and process partial pay estimates, coordinating materials testing requirements, tracking and documenting certification of materials, as necessary and completion of As-Built documents following construction.

 

Alternative Options:

Not recommended

 

Financial Impacts:                     

The action of considering a motion authorizing the Request for Proposals for the Wastewater Treatment Plant Improvements Project has no financial impacts. The City has budgeted $764,242.00 for the design work to take place in 2022. Consultants will provide proposals that include project costs for the study.

 

Tentative Timelines:                     

                     January 20, 2022                                           Solicitation for proposals begins

                     February 24, 2022                      Proposal submittal deadline

                     March 15, 2022                                           Council approve Contract with recommended firm

                     March 16, 2022                                          Wastewater Treatment Plant Upgrades Project begins

                     July 2022                                           60% Design Plans & Cost Estimate

                     September 2022                                          95% Design Plans submitted to MPCA for Review

                     October 2022                                          Design Completion and Bid

                     November 2022                                          Award Bid

                     2023                                                               Construction