File #: 25-097    Version: 1 Name:
Type: Information/Discussion Item Status: Agenda Ready
File created: 1/10/2025 In control: City Council
On agenda: 2/18/2025 Final action:
Title: Ice Arena Project Update/Cost Update in Preparation of Bidding.
Attachments: 1. 1 - Ice Arena Presentation, 2. 2 - Northfield Ice Arena DD Estimate Rev 2.11.25, 3. 3 - Ice Arena - Project Schedule 2-11-25
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Meeting Date:                      February 18, 2025

 

To:                                          Mayor and City Council

                                          City Administrator

 

From:                                          David E. Bennett, Public Works Director/City Engineer

 

Title

Ice Arena Project Update/Cost Update in Preparation of Bidding.

 

Body

Action Requested:                     

The Northfield City Council receives an update on the Ice Arena.

 

Summary Report:

The City of Northfield approved the partnership framework with the City of Dundas, Northfield School District and Northfield Hockey Association on June 18, 2024, along with the contract for the architect.

 

On September 17, 2024, the project team gave an update to Council and shared interior layouts along with exterior building options. Since then, the project management team (PMT) have been meeting with the Architect JLG and Construction Manager RJM Construction to finalize the ice arena plans.

 

As part of the Construction Manager works, they were able to price check the design development plan set for the project, which is trending 15-20% above the project estimated budget of $20.9 Million. The PMT has been reviewing value engineering options and has initially identified about $900,000 in value engineering project saving.

 

JLG Architects along with RJM Construction will give an update on the project as the plans are being finalized before project bidding occurs in March. After all the bids are in, the updated Guaranteed Max Price will be updated as part of the construction manager contract.

 

A Representative from the Northfield Hockey Association will be present to provide an update on their fundraising and donation effort. As of late January, the NHA has indicated $2.8 Million in pledges and donations

 

Alternative Options:

                     None recommended.  The existing site and arena have been sold with proceeds allocated to new construction project.  The lease on the existing building is through 2026 and was included in negotiations with the new owners for the City to vacate after completion of the new construction.  They are planning for future use of the building.

 

The current project schedule will meet the proposed lease time period.  The construction schedule is attached for reference.  The alternative option would be not to have an ice facility in Northfield which had been previously decided cooperatively with the City of Dundas (paying the same tax rate as Northfield), Northfield school district and private partners.

 

Financial Impacts:                     

See attached presentation

 

Tentative Timelines:                     

Project will be bid in March

Construction will begin in the spring of 2025

Ice Arena will open August 2026