Skip to main content
City of Northfield MN
File #: Res. 2026-012    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 9/10/2025 In control: City Council
On agenda: 1/6/2026 Final action:
Title: Consider Resolution Approving Plans and Specifications and Order Advertisement for Bids for the Spring Creek Road Reconstruction & Mill Towns State Trail Project (STRT2026-A84).
Attachments: 1. 1 - Resolution - Approve Plans and Specifications, 2. 2 - Link to Final Plans, 3. 3 - Project Location Map, 4. 4 - Intersection Improvements, 5. 5 - Project Process
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Meeting Date:  January 6, 2026

                                                                

To:                         Mayor and City Council

                      City Administrator

                     

From:   Sean Simonson, Engineering Manager

                       David E. Bennett, PE - Public Works Director/City Engineer

 

Subject: 

TITLE

Consider Resolution Approving Plans and Specifications and Order Advertisement for Bids for the Spring Creek Road Reconstruction & Mill Towns State Trail Project (STRT2026-A84).

 

BODY

Action Requested:

The Northfield City Council approves the attached Resolution (Attachment 1) Approving the Plans and Specifications for the Spring Creek Road Reconstruction & Mill Towns State Trail Project (STRT2026-A84) and Authorizes the Ad for Bid.

 

Summary Report:

City Council Accepted the Feasibility Report and Authorized Preparation of Plans and Specifications for the Spring Creek Road Reconstruction & Mill Towns State Trail Project (STRT2026-A84) at the February 4, 2025, City Council meeting via Resolution 2025-018 which included the following improvements (Attachment 3):

 

                     Spring Creek Road from Huron Court to Woodley Street (Reconstruction)

                     Mill Towns State Trail Construction - Woodley Street to Spring Creek

 

Staff held a third neighborhood meeting on Wednesday, December 10, 2025, to present final plans to adjacent property owners along the project corridor. There were no strong opinions against the design that is being proposed, and overall feedback was positive about the upcoming project.

 

The final design includes the following improvements that were added to the Woodley Street and Spring Creek Road intersection since the approval of the feasibility report: (Attachment 4)

                     High visibility crosswalk markings

                     Crosswalk warning signs

                     Overhead streetlights

                     Dynamic feedback speed sign

 

Alternative Options:

The City Council could delay this project; however, the deterioration of these roads will continue.

 

Financial Impacts:

This project will be funded through a variety of sources including Bonding, Franchise Fees, Capital Reserve Fund, Storm Fund, Sanitary Fund, Water Fund, and Municipal State Aid (MSA) The proposed project costs and funding tables are below:

 

 

 

 

 

 

 

 

Tentative Timelines:                     

See the attached project process (Attachment 4) which details the timeline for the Spring Creek Road Reconstruction & Mill Towns State Trail Project.