File #: 19-631    Version: 1 Name:
Type: Information/Discussion Item Status: Passed
File created: 12/3/2018 In control: City Council
On agenda: 1/8/2019 Final action: 1/8/2019
Title: Public Hearing - Improvement Hearing - 2019 Street Reclamation Project.
Attachments: 1. 1 - Improvement Hearing Notice, 2. 2 - Project Process, 3. 3 - Project Location Maps, 4. 4 - 2019 Reclaimation Improvement Hearing Presentation, 5. 5 - Ex Railraod Safety Improvment Measures

City Council Meeting Date:  January 8, 2019

                                                                

To:                        Mayor and City Council

                     City Administrator

                     

From:  Sean Simonson, Engineering Manager

                     David Bennett, P.E., Public Works Director/City Engineer

 

Subject: 

TITLE

Public Hearing - Improvement Hearing - 2019 Street Reclamation Project.

BODY

Action Requested:                     

The Northfield City Council holds a public hearing on the 2019 Street Reclamation Project (STRT2019-A42).  This hearing is also known as the “Improvement Hearing”.

 

Summary Report:

The City Council is being asked to hold a public hearing on the 2019 Street Reclamation Project (STRT2019-A42) regarding the improvements.  The purpose of this hearing is to allow for public comment regarding the project and the findings of the feasibility study.  The required 10-day notice for the improvement hearing was published in the Northfield News on December 19 & 26 2018, and notices (Attachment 1) were sent to property owners along the project corridor on December 18, 2018.

 

The actions requested above are required by Minnesota Statutes Chapter 429, which specifies the actions that must be taken to assess property owners for the cost of local improvements.  The City Council has moved this project forward to this point with the actions shown on the project process (Attachment 2).

 

The reclamation project includes the following streets (Attachment 3):

                     Blue Stem Court

                     Covey Court

                     Eklund Court

                     Grundhoefer Court

                     Hackerson Court

                     Kimble Court

                     Nelson Court

                     Simione Court

                     Wilson Court

                     Zanmiller Drive from Meldahl Lane to Gill Lane

                     Gill Lane from Zanmiller Drive to Lockwood Drive

                     Lockwood Drive from Meldahl Lane to Gill Lane

                     Orchard Street from Third Street to Fifth Street

                     Plum Street from Third Street to Fifth Street

                     Poplar Street from Fourth Street to Fifth Street

                     Forest Avenue from Lincoln Street to Fifth Street

                     Forest Avenue Loop

                     Third Street from Railroad Tracks to Forest Avenue

                     Fourth Street from Odd Fellows Lane to Poplar Street

 

Background

On October 16, 2018, the City Council passed Council Resolution 2018-109 that ordered the preparation of a feasibility report for the project and Council approved the feasibility report by Resolution 2018-138 on December 11, 2018. 

 

Project Highlights

Streets

All street segments proposed in the 2019 Street Reclamation Project are classified as “Local” streets in the current Comprehensive Plan, with the exception of Lockwood Drive, which is classified as an “Urban Collector”.  Soil borings have been scheduled, and it anticipated that the existing roads would have a sufficient existing gravel base to complete a full-depth reclamation on all segments.  The generated material from the reclamation process will then be re-graded and re-compacted to provide a new granular base for the street segments.  The streets will then be paved with bituminous asphalt.  Curb and gutter spot repairs will be performed as needed to provide positive drainage for the new street surface.

 

Partial/spot retaining wall replacement is anticipated as part of this project. Due to the age

and wear of the existing walls in the project location, it is anticipated that portions of these

walls will need to be removed and replaced. The areas where this work is being considered is

along Orchard Street (between Third and Fourth Street), Plum Street (between Third and Fourth Street), and Third Street (west of Plum Street).

 

Sidewalk and Pedestrian Improvements

In addition to the street improvements in this area, there are also sidewalk improvements

planned as a result of a Safe Routes to School (SRTS) Study completed in 2009. The City received a grant to complete a study that analyzed the barriers to K-8 students walking and biking to school. The report was adopted by the City Council at the February 16, 2010 meeting. The goal was to incorporate these improvements with future CIP projects. New sidewalk (SRTS) is planned to be installed on Zanmiller Drive from Meldahl Lane to Gill Lane.

 

In addition to the above-mentioned SRTS sidewalk installations, sidewalks are also proposed on Armstrong Road/Forest Avenue (From TH 19 to Lincoln Street S), Fourth Street (from Odd Fellows Lane to Poplar Street), Orchard Street (south of Fourth Street W), and Plum Street

(south of Fourth Street W). Each improvement will connect important portions of the pedestrian

system with existing sidewalk locations.

 

There are no sidewalks existing in these areas, so it is likely there will be some tree and landscaping removals to accommodate the new walk. The design will be adjusted to minimize these removals as much as possible.  In addition to new sidewalk installations, spot repairs and ADA (American’s with Disabilities Act) improvements will be made on the existing sidewalks and pedestrian ramps already in-place. 

 

Improvements to the railroad crossing on Third Street need to be completed in order to improve pedestrian safety. ADA compliant pedestrian ramps will be installed on each side of the railroad to provide a proper landing area for pedestrian travelers.

 

It should also be noted that the City’s Master Bike & Pedestrian Plan does call for shared use

lanes on Fourth Street, Orchard Street, Armstrong Road/Forest Avenue, and Lockwood

Drive. These lanes will accommodate bicycle traffic along with vehicular traffic. These lanes

will be indicated with appropriate pavement striping.

 

Sanitary Sewer and Storm Sewer

Minor repairs to the sanitary sewer will be performed as indicated in the Feasibility Report.  The majority of the repairs made are related to upgrading facilities to the current City Standards.  Storm sewer repairs are also proposed to be minimal.  Rehabilitation of existing structures and the replacement of a few structures are planned.

 

Watermain

Improvements to the public water system are required as part of this project to continue with

the City’s comprehensive plan. All new watermain will be installed using Ductile Iron Pipe

(DIP). Proposed water system improvements in the project area include replacing the existing

4-inch watermain on Orchard Street (Fourth Street to Fifth Street) and Fourth Street (Orchard Street to Plum Street) with a new 8-inch watermain to supply proper capacity for future development and fire suppression needs. This diameter watermain is the standard for small diameter watermain installation. Another improvement to the water system includes installing an 8- inch watermain on Plum Street (4th Street to 5th Street) to connect the missing watermain

system loop. Lastly, the existing 8-inch watermain on Third Street (Odd Fellows Lane to

Orchard Street) will be replaced with a 12-inch watermain to support future capacity needs

outlined in the City’s comprehensive plan.

 

The water service lines to individual residences are also proposed for replacement with 1-inch

copper lines as a part of the project. These replacements would be from the new watermain to

the property lines. This process would include the replacement of the curb stop and box.

Additional replacement of individual water service lines from the property line to the existing

building may also be included as needed and in cooperation with the homeowner. The extra

cost for these replacements will be paid by the homeowner and can be added to their primary

project assessment.

 

Railroad Quiet Zone

Staff is reviewing the supplemental safety measures that would need to be installed on Third Street to allow for a quiet zone crossing.  If the improvements are installed with the project, there are still other crossings within the City that would need to be safety measure installed.  There is a series approvals required to obtain a Federally Approved Quiet Zone.  Attachment 5 show example of supplemental safety measures that is being explored for Third Street.

 

Alternative Options:

1.                     The City Council could delay this project; however, the pavement will require significant repair work in order to keep the streets in marginal condition for traffic. 

 

Financial Impacts:

The estimated total project costs indicate there is enough funding available to complete this project.  The funding tables are below:

 

 

 

Assessment amounts are estimates at this time.  The City is in the process of completing a Benefit Appraisal.  The funding tables will be updated when the Benefit Appraisal is complete. 

 

Tentative Timelines:                     

The project process (Attachment 2) accounts for all the required actions by City Council to ensure that Minnesota Statute Chapter 429 procedures are followed so that assessments for local improvements may be levied to abutting benefiting properties.