File #: Res. 2026-039    Version: 1 Name:
Type: Resolution Status: Consent Agenda
File created: 3/24/2026 In control: City Council
On agenda: 4/7/2026 Final action:
Title: Consider Resolution to Accept Public Improvements - Wastewater Treatment Plant Improvements Project (WSTR2022-J32).
Attachments: 1. 1 - Final Acceptance Resolution, 2. 2 - Resolution 2023-048 Awarding Magney Construction Inc.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Meeting Date:                      April 7, 2026

 

To:                                          Mayor and City Council

                                          City Administrator

 

From:                                          David Bennett, P.E., Public Works Director/City Engineer

                                           Justin Wagner, Utilities Manager

 

Title

Consider Resolution to Accept Public Improvements - Wastewater Treatment Plant Improvements Project (WSTR2022-J32).

 

Body

Action Requested:                     

The Northfield City Council approves the attached Resolution Accepting Public Improvements for the Wastewater Treatment Plant Improvements Project (WSTR2022-J32).

 

Summary Report:

The contractor has completed all the improvements, and now the project is ready for City Council to accept public improvements for the Wastewater Treatment Plant Improvements Project (WSTR2022-J32).  The Wastewater Treatment Plant Improvements Project consists of additional sludge storage, primary clarification equipment upgrades, control systems upgrades, HVAC equipment replacement, roof replacement, influent lift pump replacement, card access system upgrades, office area upgrades and fence and gate updates.

 

City Council awarded the contract for the Wastewater Treatment Plant Improvement Project via Resolution 2022-048 (Attachment 2) at the June 6, 2022 City Council meeting. The contractor has submitted all the required documents as laid out by the contract.

 

Alternative Options:

This project has been completed, and the final acceptance is needed to close out the agreement.

 

Financial Impacts:

Original Contract Price: $12,271,500.00

Change Order No. 1 and 2 Increase: $612,118.01

Change Order No. 3 Decrease: $894,092.42

Final Contract Price: $11,989,525.59

 

The current change order is a deduct for allowances that were not used. In this project, the main allowance that was not used was the installation of solar panels on the rooftops. The allowance for rooftop solar was $800,000. The City will work with Xcel Energy to continue to pursue solar at the wastewater treatment plant.

 

Tentative Timelines:

Upon acceptance by the City Council, and the expiration of the two-year maintenance period, the City of Northfield will assume ownership of all installed public infrastructure.