Legislation Details

File #: PC Res. 2026-006    Version: 1 Name:
Type: PC Resolution Status: Agenda Ready
File created: 5/11/2026 In control: Planning Commission
On agenda: 6/18/2026 Final action:
Title: Consideration of a Conditional Use Permit for Off-Street Parking at 212 Division St. S.
Attachments: 1. 1 - PC Resolution, 2. 2 - Architectural Renderings 06-03-2026, 3. 3 - Floor Plans 06-03-2026, 4. 4 - PC Resolution 2023-010
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Planning Commission Meeting Date:                     June 18, 2026

 

To:                                          Members of the Planning Commission

 

From:                                          Mathias Hughey, Associate City Planner

 

Title

Consideration of a Conditional Use Permit for Off-Street Parking at 212 Division St. S.

 

Body

Action Requested:                     

The Northfield Planning Commission (PC) is asked to make a recommendation to City Council on Rebound Real Estate’s application for a Conditional Use Permit (CUP) for off-street parking at 212 Division St. S.

 

Summary Report:

The applicant, Rebound Real Estate, has applied for a CUP for 212 Division St. S. The proposed project includes a 57-room hotel, mixed commercial space (retail and restaurant space) and 19 lower-level off-street parking stalls. The site development standards for the C1-B: Downtown zoning district denote in Table 3.2-5: Historic District Sub-District standards states, “Off-street parking is allowed only by Conditional Use Permit in this sub-district.”

 

Other relevant applications and/or approvals for this project include: a variance request to exceed the maximum height limit, site plan review which covers compliance with applicable regulations including the Land Development Code, fire code, building code, ADA requirements, engineering and utilities standards, etc. A Certificate of Appropriateness for new construction in the Historic district was issued with conditions at the June 3, 2026 Heritage Preservation Commission (HPC) meeting. The approval was unanimous with one member absent. The conditions imposed by the HPC include:

-                     Matte finishes (paint) on the roof-top screening

-                     Reducing the variegation of the primary brick in the material selections

-                     Including arched-toped windows on the rear façade to match the front

-                     Providing a greater tonal differentiation between the two cultured stone selections.

-                     Final review of 30% construction drawings to confirm consistency with renderings.

 

The proposed off-street parking will be located under the ground floor commercial spaces and accessed via an easement on the west side (facing the Cannon River), and contained entirely within the building footprint. The rear of the building is proposed to include a patio on the south end, and a deck on the north, which will serve separate commercial uses. Between these spaces will be separate entrances for the parking and the commercial spaces.

 

Conditional Use Permit Approval Procedure & Approval Criteria:

A CUP follows the Type 4 Review Procedure found in Section 8.4.7 of the LDC. For the Type 4 Review Procedure, the Planning Commission holds a public hearing and makes a recommendation to City Council, and City Council makes the final decision.

 

In the approval of a conditional use permit, the Planning Commission may recommend that City Council impose such conditions as necessary to make the use compatible with other uses allowed in the same district zone or vicinity. Of the criteria, Criterion (a) is required and is met. Criteria (b) through (n) shall be considered and of those 13, 11 are met, and 2 are not applicable. A detailed analysis of the findings is included in the draft resolution.

 

The previous iteration of an infill project on this site was canceled in late 2025 due to financial infeasibility. That project received a CUP for construction of 34 off-street parking spaces, with several conditions recommended by the PC. Those conditions were related to the provision of EV ready parking spaces, adequate bicycle parking, and receipt of a COA from the HPC. The 2023 PC resolution is attached for reference. Those conditions are addressed by the changes to the parking code requirements of the City, which now require minimum bicycle parking provisions and standards, and the City’s sustainable building policy, with the applicant pursuing a B3 certification.

 

Minimum bicycle parking for the site, based on LDC requirements, is 12 spaces, half of which must meet the standards of long-term bicycle parking. The previous conditions required 1 long-term space per long-term rental and 1 space per 3 short-term residential unit, plus 12 short-term spaces split between the east and west sides of the building. The proposed hotel use is anticipated to generate lower demand for bicycle storage and therefore staff is not recommended additional bike parking spaces or conditions other than the 12 required spaces per the land development code.

 

All vehicle parking spaces are currently proposed to be EV ready based on the B3 requirements.

 

Staff Recommendation:

Staff recommend the Planning Commission recommend approval of the CUP of 19 off-street enclosed parking spaces to City Council.

 

City Plans & Policies Relevance:

A detailed assessment is provided in the Findings attached to the resolution because one of the findings is consistency with City plans and policies.

 

Alternative Options:

If the proposed conditional use satisfies both the general and specific standards set forth in the zoning ordinance, the applicant is entitled to the conditional use permit. Importantly, if the applicant meets the general and specific ordinance standards, the city usually has no legal basis for denying the CUP.

 

Financial Impacts:                     

NA

 

Tentative Timelines:                     

June 3, 2026 - HPC COA Preliminary Approval

June 18, 2026 - Zoning Board of Appeals Hearing and Decision on Height Variance

June 18, 2026 - Public Hearing and Planning Commission Recommendation on CUP for Off-Street Parking

June 27, 2026 - Initial 60 day review timeline for site plan - to be extended

July 1, 2026 - HPC review and acceptance of 30% construction drawings

July 7, 2026 - City Council Decision on CUP